Cutting the cost of a load
Heathcote users cutting their peak charges and avoiding the upgrade
From 2033 Heathcote runs about 8.8 MW short at peak.
The gap lasts over four hours, morning and evening. Orion has not chosen a fix. Bromley, above it, runs short from 2031.
Orion AMP 2026, Commerce Commission disclosure, Transpower 2026
Open the Heathcote card to see the evidence →Winter peak against what Heathcote can carry, MVA
Winter peak, now, in five years and at its lowest roomWhat the substation can carry
A worked example from public data. Savings depend on how your site is metered and when it peaks, and on Orion's own terms. It is a screen, not a tariff quote or advice.